URGENT NEWS!!!! - WATER PIPE REPLACEMENT PROGRAMME
Tuesday, 8 Jan 2008
|
Over the next two years United Utilities will be undertaking a programme of work throughout the city to replace old cast iron water pipes with new plastic ones. This work will begin in the Northern Quarter from Friday 11th January.
In an attempt to help minimise disruption, Cityco(the City Centre Management Company), will be publishing a list of locations and timetables for all of the planned work.
Over the next two years United Utilities will be undertaking a programme of work throughout the city to replace old cast iron water pipes with new plastic ones. This work will begin in the Northern Quarter from Friday 11th January.
In an attempt to help minimise disruption, Cityco(the City Centre Management Company), will be publishing a list of locations and timetables for all of the planned work.
IDENTIFIED TIMETABLE :-
INFORMATION CARAVAN SITUATED
ADJACENT TO CRAFT CENTRE (OAK ST) 15th/16th Jan
ROMAN STREET/EDGEHILL STREET 11th/12th/13th Jan
" " " " 18th/19th/20th Jan (Provisional)
COOP STREET/FOUNDRY LANE 14th Jan 7 days
OAK STREET 14th Jan 7 days
SILVER JUBILEE WALK(OAK ST-TIB ST) 21st Jan 7 days
BRIGHTWELL WALK 21st Jan 7 days
OAK STREET(THOMAS ST-BRIGHTWELL WK) 28th Jan 14 days
EDGE STREET 11th Feb 11 days
MARTLESHAM WALK/LEN COX WALK 11th Feb 11 days
TIB STREET End of March (Provisional)
THOMAS STREET Beginning of April (Provisional)
Please note that the information published is the most current available to Cityco and it is subject to change, so please check back regularly for updates.
If you require any further assistance please call Tommy Wolstencroft on 0161 234 4010
|
|
|